Viewing Grant Proposal: Electric City ESS (Sturgis)_Battery Storage Facility
With a proposed 9.8MW x 39.2MWh battery storage project known as Electric City ESS, the City of Sturgis aims to bolster its distribution system and continue its legacy of innovative energy solutions. Electric City ESS is a planned battery storage project to be interconnected within the City of Sturgis Michigan’s Electric Department municipal utility. Electric City ESS has been designed as a 9.79MW maximum output (inverter nameplate capacity) x 39.16MWh (battery capacity) system giving the project an approximate 4-hour output duration at maximum power. The planned storage system incorporates distributed inverters within the enclosures along with the battery modules. Power leaves the enclosures at 480V 3 phase and is subsequently stepped up to 12.47kV via a series of transformers. The 12.47kV system then interconnects to the City’s electric grid.